Moving bundles of cut transformer core laminations from a cutting table to a pallet calls for more than lifting capacity. The load needs support, controlled movement and access to the receiving position.

In this application, PM Powerful enables one operator to handle bundles weighing up to 1,000 kg. Pneumatic motors provide rail travel and main-axis rotation, helping the operator guide the load from the machine to the pallet.

The installation comprises two independent manipulators, each with a 1,000 kg capacity and its own 24-metre overhead rail. Each unit is operated by one person and serves one of the machine’s two opposing tables.

Two Independent Handling Systems

The Powerful pneumatic manipulators used in this project are configured for 1,000 kg each. Their separate rail systems allow each operator to move loads within the respective working area.

The layout connects the machine’s unloading positions with the pallet locations along each rail. Capacity, travel distance and access to the load are addressed together as part of the handling arrangement.

Supporting the Bundle from Below, Clamping from Above

The custom gripper combines fork supports beneath the bundle with a pneumatic clamping mechanism above it.

The forks carry the load from underneath. A pneumatic cylinder operates the upper clamp to hold the bundle in place during transfer. This arrangement helps limit movement within the gripper when the load is moved or positioned.

The product being handled is a bundle of cut core laminations, ready for the subsequent packaging stage.

Pneumatic Travel and Rotation under Operator Control

Pneumatic motors drive movement along the rail and rotation about the manipulator’s main axis. The operator manages these movements using the controls on the gripper.

The handling sequence is straightforward:

  • Position the forks beneath the lamination bundle.
  • Secure the bundle with the upper pneumatic clamp.
  • Lift and guide the load along the rail.
  • Position it on the pallet and release the gripper.

The combination of supported gripping and powered movement allows the operator to control the transfer from pick-up to placement.

Engineering Around the Production Layout

For a production team assessing this type of application, load weight is one part of the specification. Access beneath the bundle, table positions, the transfer route and pallet locations also determine the handling arrangement.

For example, where pallet positions are distributed along a cutting line, both rail coverage and gripper access need to be considered when defining the solution.

In this project, ERHA Engineering designed and manufactured the complete PM system, including the supporting steel structure, rail systems, manipulators and custom grippers. The pneumatic arrangement was developed around the same operating layout.

The application illustrates how metal handling and positioning can be planned as a complete transfer operation, from the machine interface to the receiving pallet.

Handling Applications at GEORG and LAE Machines

PM manipulators also support transformer lamination handling operations at GEORG and LAE machines.

Discuss Your Handling Application

Share the load weight, dimensions, available gripping points and production layout.

Contact PM to discuss a handling solution for your operation.